8.1 – Table Quiz 1

Duration of the production cycle of one batch

Fill in the blanks. Enter calculated answers in whole numbers. So, no decimal numbers!

Production time = Dosing and weighing + Grinding + Mixing
Capacity = Batch size ÷ Production time × 60

Batch size 1000 kg 5000 kg 10000 kg
Dosing and weighing 10 min. 6 min. 8 min.
Grinding 10 min. 6 min. 12 min.
Mixing 5 min. 3 min. 2 min.
Production time of one batch 25 min. min. min.
Capacity 2.4 t/u t/u t/u